Because of our current situation and the continued Covid restrictions we are shifting our building plans to preparation for construction. We are now working on the center of our building. This involves joining the two bottom sections to make a large meeting/dining room area. This is sorely needed for our school. At the back will be a large kitchen area. In the middle will be the dining area and meeting room. At the front will be a library and office (I think).
Here is a rough layout diagram. The yellow area is the kitchen at the back. The size is about 10 meters by 3 meters. The meeting area is about 10 meters by 8 meters. The front office area is about 10 meters by 4 meters.
We have completed taking down the two inner walls and the old floor tiles using a sledge hammer and jackhammer. A final decision hasn't been made yet for the rest of the main structures. Here are some pics of the kids helping with destruction!